18 September 2020 --Requirements List Update-- Items in Mandatory: Freeware: Christrains Scenery Pack (Station Objects and Scenery) with ATB and...
12 September 2020 7:45-7:55 AM Canopy placement at Meycauayan. Platform height adjustment and Canopy Placement at Marilao, Bocaue and Balagtas....
When this route was released on Steam yesterday (11 September 2020), I click the "View the manual" link to show the route manual for this route....
Antipolo City, Rizal, Philippines
7 September 2020 Platform height adjustment and Canopy placement at Caloocan and Valenzuela. Platform height adjustment at Meycauayan. Notes:...
18-27 August 2020 18 August 2020 Platform adjustment at Buendia and Paco. Canopy placement at Buendia and Paco. 19-26 August 2020 No Work --...
Short video was made about Random Emergency Braking on this route. Most incidents happen at Worgl, OBB Protection Signals in Stations shows clear...
Problems experiencing ICE 3 (video) Jump to 16:56 to 17:13 and 23:44 (Note: Needs PC Browser to work) [MEDIA] I am not sure if all problems...
What graphics driver version you use? Got this yesterday
Oops, wrong forum. This is TS2020 forum. Train Sim World forum is here: Link to the forum: https://forums.dovetailgames.com/forums/trainsimworld/...
17 August 2020 --New Schedule Update-- Schedule Notice: Same Schedule will continue until 31 August 2020. Wait until further notice if another...
Music is preferable to me. I would go here: http://trainsimlive.tv/so-you-want-the-tsl-in-game-background-music-heres-how/ I don't know if we can...
12 August 2020 Minor Platform adjustment at Sucat. Canopy placement at: Sucat, Bicutan, FTI and Edsa. Timeframe: 9:25-9:40 AM GMT+8 Philippine...
All workshop routes/trains/asset packs/marketplace add-ons affected the same way. Ex. DB BR 101 Add-on, LGV Marseille - Avignon, etc. Both happens...
30 July-4 August 2020 30 July Platform height adjustment at San Pedro. Canopy placement at Pacita and San Pedro. 4 August Platform height...
5-6 July 2020 and 29 July 2020 --Mamatid platform height was adjusted and canopy placement without log between 7-28 July-- 5 July 2020 Removed...
1 July 2020 Series of compatibilty tests commenced. This route will now require Brennerbahn (Tirol: Brenner - Kufstein DLC). Tests conducted:...
26 June 2020 Placed platform on LRT Bluementritt Station area, but removed bridges on it. Working on speed limits from Calamba to Malolos. (Part...
24 June 2020 NSCR Tracks placed until San Fernando. Small river placed in San Fernando. Embankment placed on Apalit - San Fernando segment. New...
22 June 2020 --Temporary Notice-- The tracks should be placed until San Fernando yesterday, but unstable internet connection (Everytime I build...
Hamburg - Hannover Tracks
18-20 June 2020 18 June 2020 Reviewing Pond Placement at Obando. Some adjustments to terrain needed. Adjusting loft height at Meycauayan River....
Route Builder, Philippine National Railways: Luzon System. Route is Open for Collaboration.
17 June 2020 Pond placement at Obando and adjusting terrain. (Stage 2 - Under review on 18 June 2020 AM Time GMT+8 Philippine Standard Time)...
16 June 2020 11:05 AM-1:15 PM Minor track removal at Valenzuela Depot. (Switchback to Shop and Siding) Track laying until Balagtas. New NSCR...
15 June 2020 Valenzuela Station. (Constructed Main Line and Station. Linked from Depot to Main Line.) Last 6 May 2020, the depot was constructed....
15 June 2020 Evaluating Catenary to use on NSCR Segment. Signal Testing on Valenzuela Polo. KS Signals will be selected. Constructed Valenzuela...
14 June 2020 11:30 AM-12:10 PM Marks the start of NSCR North Construction. Tracks placed until Caloocan. Removed current bridges in use (LGV) to...
14 June 2020 Embankment Segment between Caloocan and Malabon: First 2 pictures are views from Caloocan Side. [ATTACH][ATTACH] Remaining 2...
14 June 2020 Notice: Please standby where the route will be uploaded (collaboration copy). Tried the "Resources" section but it fails due to size...
To prevent any copyright infrigement or grabbing photos without permission. Mark
9 June 2020 --This dates from 30 May 2020 to 5 June 2020-- Sta. Rosa Area: Constructed road bridge instead a Level Crossing to prevent any rail...
30 May-5 June 2020 30 May 2020 9:10 AM-12:15 PM Removed more whistle boards at Sta. Rosa. Temporary Track placed until Sta. Rosa. NSCR South...
Good Idea as well. Should happen as a "Pro Range" model. Should have TVM + ETCS Signalling Pack included on this train. :)
8 June 2020 Additional Guidelines for Collaboration Once NSCR North, NSCR South is finished, I will release the "For Collaboration Use" in...
If the update happens to really Pro Range, is it compatible to current TGV Duplex unit included in LGV: Marseille Avignon?
29 May 2020 --Follow-up-- Route Building will be moved by Tomorrow (30 May 2020) because of: Possible bad weather this afternoon/evening (6PM...
29 May 2020 The Following will be Collaborated: (Experts and Route Builders are welcome): [ATTACH] Scenery Terrain Paint Clutter Trackside...
Hi 749006, Thank you for supporting this project. xD The pictures/screenshots can be found here:...
27 May 2020 --Missing Assets (Follow-Up)-- A fix was arrived by DTG this morning and the missing UK LED Signals is fixed. The route building will...
Update 27 May 2020 Tested any scenario affected and now it works after the fix arrived this morning by DTG (UK LED Signals and Class 370 now...
Update (25 May 2020): (More scenario testing of affected routes this morning) On WCML North, Class 47 Large Logo scenario (EU Loco and Asset...
No changes to tracks/signals (tracks.bin related) to any of the routes above. Only used for inspecting the signal links and closing the route...
Note: This is an additional issue not just the Missing Item (UK LED Signals). It happens on the following routes: London to Brighton WCML North...
23 May 2020 --Warning: Missing Assets-- The route building will take place today, after suspension last May 19-22 due to emergency trip to...
18 May 2020 Terrain Data imported in the following areas: 10:10-10:30 AM Rest of Batangas Tiaong (Quezon) Candelaria (Quezon) Sariaya (Quezon)...
17 May 2020 Notice: Track laying will be suspended temporarily, until all SRTM Data is placed. Reconstructed Biñan River. Constructed Tunasan...
Where to get this train? Thanks.
16 May 2020 Applied superelevation at Muntinlupa - San Pedro segment. Reconstructed Poblacion River at Muntinlupa. Removed whistle boards at...
14-15 May 2020 14 May 2020 Pocket track for Temporary line placed at Bicutan. Test run of Class 390 GNER S9BL at York - Peterborough route. 15...